- State of the art distribution facility at Turbine Business Park
- Occupied by Vantec and will handle over 6m plastic and metal containers containing Nissan car parts each year
- Delivery was crucial to ensure that both Vantec and Nissan’s operational requirements were met
- The external works were complete in 30 weeks allowing partial handover for internal fit-out/occupation by Vantec at week 22 of the build period
- Project was delivered on time despite over 500 man hours being lost during the contract period due to inclement weather
- Client – Barmston Developments
- Duration – 30 Weeks
- Size – 422,000 sq ft