D-Campus, Sheffield

  • Construction of 2 No 50,000 sq ft buildings
  • Building 1 on 4 levels, whilst building 2 was on 5, both with impressive ground floor reception areas and double height feature reception
  • Constructed with a mixture of high quality curtain walling and stone cladding the buildings were designed to be modern and minimal throughout
  • Another notable feature is the ‘helter skelter’ which enables quickly travelling from the top to ground floor
  • The project included the construction of public concourse area with extensive highway/junction improvements to optimise traffic flow
  • BREEAM ‘Very Good’

Project Details

  • Client – Valad Property Group/Sheffield City Council (fit out)
  • Duration – 96 Weeks
  • Size – 100,000 sq ft

“GMI’s professionalism and pro-active nature helped the whole client team work well together and meet the client’s brief to a high quality standard. At many times throughout the construction process, GMI demonstrated their ability to pre-empt issues and assist the client team in making informed decisions for the betterment of the projects as a whole. GMI’s commitment to maintain a challenging programme within budget was testament to this.”
Patrick Durkin, Gardiner & Theobald LLP